Skip to content

Production Schedule

Create a production schedule for next year. The goal of the schedule is to demonstrate that the plan defined in your game design macro is feasible.

As you consider feasibility, there are some important details to keep in mind. First, the exact composition of your team is subject to change, and you may need up to a week at the beginning of production to re-orient the team and adjust your schedule. This is therefore a case where “plans are useless but planning is essential,” as Eisenhower said.

The schedule should account for approximately 21 weeks of production in CS414–415. Each team will be expected to complete an alpha milestone before Thanksgiving break and a beta milestone in the middle of the subsequence Spring semester. After that, the team will shift into post-production. You can peruse Lemarchand for formal definitions, but suffice it for our purposes to think of alpha as feature complete and beta as content complete.

Lemarchand Chapter 19 assumes that all production tasks are best distributed to individual team members. While this is true for some production tasks, the text ignores integration costs as well as the productivity benefits of Software Teaming, also known as Mob Programming.

One useful way to approach the schedule is to frame the work using user stories. As long as you keep in mind the definition of done for each feature thus described, you can frame all your work as user stories and estimate these as hours or days of team effort.

Regardless of what strategy you use to construct the schedule, the goal is the same: to emerge from preproduction with a reasonable and defensible argument that the game described in your macro can be built by you during production.

A satisfactory schedule will account for all of the following:

  • feature development
  • art and sound
  • playtesting
  • interface needs
  • marketing materials

Excellence in the schedule can be earned by serving as the primary author and reviewing a reasonable rough draft with the instructor at least two weeks before the deadline.